Project: YEREVAN (ARMENIA) COMBINED CYCLE POWER PLANT 2 - 2019-2020 year.
Country of origin: Germany.
Country of delivery: Yerevan, Armenia.
Place of loading: Port of Poti, Georgia.
Key Logistics Data:
Railway: Lashing/Securing of 188-ton transformer / 167 ton Generator / 205 ton Gas Turbine loaded on special 16-axel railcar.
Road: 33x40’ containers, 35 tilt trucks, 21 flat trucks.
Scope of services:
Railway: Drawings & Calculations for authorization of special rail Permissions, Mock-up test layout construction for heavy lifts permission acceptance by Georgian Railway, Supervision of cargo loading onto special 16-axel line 225 loading capacity railcar, lashing and securing.
Road: Transportation of 33 SOCx40’ containers, 35 tilt trucks, 21 flat trucks up to destination site.